Sprint 11
KW 46-47, 11.11.13 - 22.11.13
Abstract
This Document is a short summary of development activities during Sprint 11 of myRIO Balancing Robot development.
It is part of the agile development model used for the development of myRIO Balancing Robot as described here: https://decibel.ni.com/content/docs/DOC-30572 and https://decibel.ni.com/content/docs/DOC-32062
Developers
Adrian Schmid, 100%, 30 Story Points
Team TU-Darmstadt, 25 Story Points
Team DHBW, 25 Story Points
Jean Mallo, 25%, 7.5 Story Points
Team Capability
87.5 Story Points
Initial Sprint Backlog
U-048: Controller, 20 Story Points
U-049: User Interface, 20 Story Points
U-037: Prototype Redesign (ADP, TU-Darmstadt), 25 Story Points
U-050: VT Implementation: Teaching, 20 Story Points
U-052: Co-Simulation, 20 Story Points
Total: 105 Story Points
Impediments
Impediment 1: U-052 Co-Simulation
U-052 was changed to Epic.
U-053 - U-055 introduced.
Impediment 2: Jean Mallo
Jean Mallo stopped working on the project.
Released
U-048: Controller, 20 Story Points
U-049: User Interface, 20 Story Points
U-037: Prototype Redesign (ADP, TU-Darmstadt), 25 Story Points
U-050: VT Implementation: Teaching, 20 Story Points
Total: 85 Story Points
Burndown Chart