07-14-2012 05:39 PM
I have try to get a plot over long time, 1 to 24 hours and more than 2 channels, up to 6 channels in same graph. What I have try is to use a xy plot and then by letting the x axis min max be controlled, see picture, the thing is you can only use 2 channels to data on a xy plot, if I those a chart plot, when i use the same structure to control the max min for time span, no lines are plotted for some reason, see picture.
Regards // Thanks
Lars
07-16-2012 06:44 PM
You can put as many XY plots on one XY graph as you like, there should be an example for multi-plot XY (dont have LV infront on me right now). you can build up in an array the X and Y values and periodically regraph them. Change the X scal as you wish or just replot a subset of each XY plot.