that was the problem... but raises another issue.
My DAQ device NI-USB 6008 was not connected to my "development workstation" but was on the "distribution workstation". When I connected the USB DAQ device to my development workstation I was able to check the checkbox and it was included in the configuration file and when I installed the application on the development workstation, it worked as expected.
Does this mean that any time I make a change to the "Task" i'm going to have to have the DAQ device (the UB 6008) attached to my development workstation for the installer build to work?... that seems cumbersome... and since I'm going to be developing my App to run on 4 different workstations each with it's own USB 6008, am I going to have to configure the appln 4 ways (4 tasks) - 1 for each workstation?