how change the report graph color in teststand

how change the report graph color in teststand?
0 Kudos
Message 1 of 5
(3,977 Views)
Mamp,

While most of the colors in the report can be changed simply by going to Configure>>Report Options and clicking on the Report Colors button, the report graph does not expose that ability. The graph is an activeX control and it does not have a method or a property exposed to change the color. If changing the color is still a requirement, it is always possible to modify the report generation to include your own custom graph generation. As with many features in TestStand, the report generation is fully customizable.

Hope that helps.

Regards,
Shannon Rariden
Applications Engineer
National Instruments
0 Kudos
Message 2 of 5
(3,977 Views)

Shannon,

 

Can you go into further detail as to how to include your own custom graph generator?

 

Thanks,

 

Michael Sumulong

0 Kudos
Message 3 of 5
(3,452 Views)

Michael,

 

You might also be able to customize the style sheet associated with the report. The TestStand Help provides some information about how to customize ATML or XML style sheets to change report colors based on the status of test steps.

 

Please take a look at the following topics; are these helpful?

 

ATML Report Style Sheets

Modifying Cell Background Color Based on Step Status in ATML Test Results 5.0 Reports

 

XML Report Style Sheets

Modifying Cell Background Color Based on Step Status in XML Reports

Tom
TestStand Documentation
0 Kudos
Message 4 of 5
(3,442 Views)

I have tried to follow the directions mention for xml report cells (expand.xls) . But I still cannot change the status cell background color for Multiple numeric array tests.

 

jjsmith777_1-1648936820934.png

Any help is appreciated.

0 Kudos
Message 5 of 5